Subject: | "User Employee Rate" is not functional under "Customer Project/Rates". |
Summary: | The following was done. - Add activity "Accommodation" to project "JIWA Financial".
- Added project "JIWA Financials" for customer "CK".
- Set the rate to "Use Employee Rate" for the project "JIWA Financial" under "Customer Project/Rates" for customer CK.
- I created a time entry for employee E001, the system picked rate as 1. Please advise where its been extracted
|
Audit Notes: | Edited by sanjay on 08/12/20 09:20. Edited by rashna on 21/06/19 10:08. |
29 May 2019 | 01:35PM Comment 1 by Rashna (Edge Business Solutions) Case 10422 added to project 11.0 |
12 Jun 2019 | 01:05PM Comment 2 by Rashna (Edge Business Solutions) Assigned To: Rashna (Edge Business Solutions) Followup Date: 12-06-2019 01:05 PM Time Taken: 1.50 Notes: Edited by rashna on 21/06/19 10:15. |
| Hi Rashna, The "Use Employee Rate" flag uses the rates defined in "User Maintenance" regards Alvis |
|
21 Jun 2019 | 10:14AM Comment 3 by Rashna (Edge Business Solutions) Assigned To: Alvis (Link Technologies) Followup Date: 28-06-2019 12:00 AM Time Taken: 2.50 |
| Hi Alvis, I tested the case as per comment 2, however, the rates were picked from user maintenance. Steps to Replicate - Set the rate for "company 1001" for user "Alvis" as 33.33.
- Navigate to "Time Maintenance - Customer Project/ Rates"
- Select customer "CK"
- Set "Use Employee Rate" for project "Link HR".
- Login as "Admin" and create the time entry for "Alvis". The entry does not pick rate in 1 above.
|
|
24 Jun 2019 | 09:39AM Comment 4 by Sanjay (Link Technologies) Assigned To: Development Followup Date: 24-06-2019 09:39 AM Time Taken: 2.50 |
| Development work for this case has been completed. The change will be available in version: 11.0.0624 1. The following changes were made(Include Database object names, Program classes and any other relevant information):| - Corrected the get rate procedure to use loaded employee id instead of the logged in username
2. The issue was caused by: - Incorrect username used to get rate.
3. Next Step: - UAT
4. Notes: |
|
26 Jun 2019 | 02:32PM Comment 5 by Rashna (Edge Business Solutions) Assigned To: Sanjay (Link Technologies) Followup Date: 26-06-2019 02:32 PM Time Taken: 2.50 |
| QA Results Tests carried out according to requirements specified on the case header Test Results Summary Table 1 - Summarised list of issues No | Test Description | Pass/Fail | 1 | - Set the rate for "company 1001" for user "Alvis" as 33.33.
- Navigate to "Time Maintenance - Customer Project/ Rates"
- Select customer "CK"
- Set "Use Employee Rate" for project "Link HR".
- Login as "Admin" and create the time entry for "Alvis". Rate of $33.00 should be depicted
| Pass | 2 | Log in as "Alvis" and create time entry with above details, rate of $33.00 should be depicted | Pass |
Documentation has been updated at this link. Environment Details - OS version: Windows Server 2012
- Application version: 11.0.0624 BETA
- Setup: Demo
- Server : 10.0.0.14
- Database: LINKSOFT-DEMO-11-RASHNA
Next Step: Closure
|
|